Most homeowners guess whether their project needs a grading permit based on how disruptive it looks. Los Angeles doesn't decide it that way. The line is a cubic-yard count, and there are three of them, each triggering something different: whether you need a permit at all, whether a licensed civil engineer has to stamp the plan, and whether you need to post a bond before work starts.
What a grading plan actually is
A grading plan governs the earthwork on a lot: the cuts, the fills, and the finished shape of the ground. "Cut" is earth removed by artificial means; "fill" is earth deposited by artificial means. The plan shows how much of each, where, and to what final elevations. A drainage plan is a different document that governs where water goes once that earthwork shape is set, and on many LA projects the two are filed together, which is why you'll see the phrase "grading and drainage plan." Our guide to drainage plans covers the three triggers that decide when LA requires one; this guide is about the earthwork side: when a grading permit is required, what the plan has to show, and who has to sign it. For the basics of grading itself, see what grading is in construction.
The three numbers that decide what you need
Before you get to yardage, LA's own list of grading work is worth checking your project against directly. LADBS requires a grading permit for any grading work in the hillside grading area, removal and re-compaction, or backfill, and its list of covered work includes slope and landslide repair, tract and mass grading, site preparation, basement and pool excavations in hillside areas, and retaining wall cuts and backfill. If your project matches one of those descriptions, assume a permit applies and confirm from there.
If it doesn't obviously match, the yardage does the deciding. Three thresholds cover almost every residential case in the city:
- Under about 50 cubic yards. LAMC 91.106.1.2 exempts a shallow excavation (under 2 feet deep, or not creating a cut slope over 5 feet high and steeper than 2:1) or a shallow fill (under 1 foot on ground flatter than a 10% slope) from needing a grading permit at all, unless the volume exceeds 50 cubic yards or the work alters existing drainage patterns. Stay under that line, on flat enough ground, and you may not need a grading permit for the earthwork itself.
- Over 5,000 cubic yards, or any hillside-area work regardless of yardage. LAMC 91.7004 classifies grading in a designated hillside area, or any grading exceeding 5,000 cubic yards of cut, fill, or combined, as engineered grading, which requires a plan prepared by a licensed civil engineer. Grading under that volume outside a hillside area is regular grading by default.
- 250 cubic yards or more in a hillside area. LAMC 91.7006 requires the owner to file a surety bond once hillside excavation or fill reaches 250 cubic yards, with the amount scaling by volume: $1,000 plus $1 per cubic yard from 250 to 10,000 cy, $11,000 plus 50 cents per additional cubic yard up to 100,000 cy, and $56,000 plus 35 cents per additional cubic yard beyond that. LADBS can waive the bond for non-hazardous work that complies with department orders.
One relief valve worth knowing about: LADBS offers an express permit, with no plan check, for grading that doesn't require plan review, doesn't remove lateral support from a public way or an adjacent structure, and doesn't require a soils report. If your project is small and simple in scope, ask whether it qualifies before assuming you're in for a full plan-check cycle.
Regular grading vs. engineered grading
Once your project crosses into hillside-area work, or 5,000 cubic yards anywhere in the city, it becomes "engineered grading" under LA's code, and the plan has to come from a licensed civil engineer rather than being handled informally. Below that line, outside a hillside area, it's "regular grading," and the requirements are lighter. This is a permit-classification distinction specific to LA's code, not the same thing as the general geotechnical terms "engineered fill" and "non-engineered fill," which describe whether compacted soil was placed and tested to a specification versus dumped without control. LA's own code doesn't classify grading by that fill-material distinction; it classifies by hillside location and yardage, as above.
What's on the plan, who signs it, and who does what
LAMC 91.7006 requires grading plans to be prepared and signed by an individual licensed by the state to prepare such documents, and to show property limits, existing ground contours, cut and fill locations and disposal sites, nearby structures within 15 feet, and drainage details when applicable (our drainage plan guide covers what those drainage-specific requirements involve). For engineered grading specifically, under LAMC 91.7004 the plans and specifications must be prepared by a civil engineer.
On a hillside or engineered-grading project, more than one professional is usually involved, and each has a different job. Per the county's documented grading framework, which mirrors how LA's own engineered-grading process is structured, the civil engineer designs the grading geometry and certifies the finished work matches the approved plan; a geotechnical (soils) engineer is responsible for testing and certifying soil compaction, typically through field density tests taken during the work; and when bedrock excavation or geologic hazards are involved, an engineering geologist inspects and reports on those conditions separately. If a contractor tells you they'll handle all of this themselves without naming a separate engineer, ask who is actually signing each part of the package.
How to read a grading plan
A grading plan can look like a page of squiggles until you know what each mark means. Start with the legend in the title block, since abbreviations vary between engineers. Then look for these:
- Existing and proposed contours. Contours are lines of equal elevation. One grading contractor's guide puts the convention simply: "Existing grades are usually dashed lines; proposed grades are solid." Where the solid line sits lower than the dashed one, earth is being cut. Where it sits higher, it's being filled.
- Spot elevations. These are "Single points marked with a "+" and a number (for example, +100.5)." The same guide advises trusting the spot elevation when it and a contour disagree, since spots are usually set at the points that matter, such as corners, drains and door thresholds.
- The benchmark. Every elevation on the sheet is measured from one fixed point, which might reference "a manhole rim, curb, or known survey point." If the benchmark is wrong or disturbed, every number on the plan shifts with it.
- Finished floor. The pad or finished floor elevation of the house is the anchor for the rest of the design. Ground around it should fall away; the guide's rule of thumb is "usually at least 2% for the first 10 feet," and the building code sets its own minimum that your engineer designs to.
- Drainage arrows. They "Indicate the direction surface water will flow across the site." Follow them to see where water ends up, and check that it reaches a drain, a swale or the street rather than a neighbor's yard.
- Earthwork quantities. Many plans include a table of cut, fill and export or import in cubic yards. That number is what sets your permit path under the thresholds above, and it drives the trucking line in any bid.
In our experience, the fastest way to check a plan is to pick a spot you know, such as the back door, and trace the arrows from it to the property line. If you can't follow the water, ask the engineer to walk you through that path before the plan is submitted.
Inspections and getting to final sign-off
Grading on an engineered project typically moves through a similar staged process to the one documented in the county's grading guidelines: a pre-grade meeting before work starts, where the consultants line up on the plan; an initial inspection after the site is cleared but before fill placement begins; a rough-grade inspection once approximate final elevations and drainage are in place; and a final inspection once the work is complete. Per that same framework, closing out the permit typically means submitting an as-built grading plan certified by the civil engineer, a geotechnical engineer's report showing field density test results, and the grading contractor's certification that the finished work matches the as-built plan. LADBS's own Grading Division inspects foundation excavations, grading, and fill placement throughout this process.
What happens if you grade without a permit
In our experience, grading without a required permit in LA carries real risk: a stop-work order that halts the job mid-progress, fines that accrue the longer the violation continues, and non-compliance fees on top of whatever permit you eventually need to pull. The city does maintain a retroactive permitting path that can legalize unpermitted work without requiring demolition, as long as the finished grading meets current zoning and code standards, but that route costs more and takes longer than getting the permit before you start. Confirm current enforcement specifics for your situation directly with LADBS rather than relying on a general estimate.
Budgeting and getting a permit
We couldn't find a single current, LA-specific grading fee figure worth quoting here, since the amount depends on project scope; LADBS publishes its own fee schedules and calculator, and that's the source to check for your specific project rather than a generic number. What we can say directly: engineered grading costs more than regular grading, since it requires a civil engineer and often a geotechnical engineer on top of the contractor, and a required soils report adds both cost and time to the front end of the project, especially on hillside lots where geologic conditions have to be documented before plan check can move forward. For what the soils work itself costs, including the report review fee and compaction testing visits, see our soils report cost guide. For how cut, fill, export and import quantities drive the grading price, see our cut and fill cost per cubic yard guide.
Once you have a permit path in hand, our guide on checking a California contractor's license covers how to vet whoever executes the work. If grading is creating the need for a retaining wall, our retaining wall design guide covers that separately, and if your lot is already actively moving rather than being newly graded, see our hillside stabilization guide instead. Medici Construction Group is one licensed option for grading work, holding California A, B and C-10 licenses under CSLB #1114433.
Frequently asked questions
What is a grading plan?
A document that governs a property's earthwork: the cuts, fills, and finished ground shape, including quantities and elevations. It's a different document from a drainage plan, which governs where water goes once that shape is set.
Do I need a permit for grading in Los Angeles?
It depends on what you're doing and how much earth is involved. Certain work (hillside excavation, retaining walls, basement or pool excavation in hillside areas) generally requires one outright; otherwise, staying under about 50 cubic yards on shallow, flat-enough ground may exempt you.
How much does a grading plan cost?
It varies by project scope. LADBS publishes its own fee schedules and calculator, which is the right source to check for your specific project rather than a generic figure.
How long does it take to get a grading permit in LA?
There's no single published timeline; it depends heavily on whether your project needs full plan check, whether it qualifies for LADBS's express (no-plan-check) permit, and whether a soils report is required, since that adds a review step before plan check can proceed.
Is a grading plan the same as a site plan?
No. A site plan typically shows the overall layout of a property (buildings, setbacks, parking, landscaping). A grading plan focuses specifically on the earthwork: cuts, fills, contours, and drainage-related grading details.
What's the difference between a grading plan and a drainage plan?
A grading plan governs the shape of the ground; a drainage plan governs where water goes once that shape is set. They're often filed together as one submittal but answer different questions.
Do I need a grading plan for a small backyard project?
Check your actual cubic yardage against LA's exemption line before assuming a small-looking project is in the clear. A backyard job that looks minor can still exceed the yardage or slope thresholds that trigger a permit, particularly on a sloped lot.
How do you read a grading plan?
Start with the legend, then compare the dashed existing contours to the solid proposed ones to see where earth is cut or filled. Spot elevations, the benchmark, the finished floor elevation, drainage arrows and the earthwork quantity table tell you the rest.