In our experience, the most expensive part of a tenant improvement project is often a space that isn't open yet. The lease is signed, rent or a rent-free period is ticking and the suite is still dark. When that happens, the cause is rarely the carpenters or the electricians. It's usually a decision that came late, a review nobody planned for or a piece of equipment ordered after it should have been.
In our experience, tenant improvement construction, or TI, is largely won or lost before construction starts. Here's how the process runs from lease to opening day, and where the time goes.
Quick answers
- What it is: the work that fits out a leased commercial space for a specific tenant.
- The order: confirm the use, choose how it's delivered, design, get plans reviewed, order long-lead items, build, inspect and get final sign-off.
- Who reviews: in Los Angeles, in our experience, Building and Safety, often the Fire Department and, for food uses, County Public Health.
- Who does what: the lease decides; our guide to shell and tenant improvement work covers the split.
Before the lease is signed
In our experience, the most useful work happens before the signature. The key questions are whether the space is approved for the use you plan, what the existing building systems can support and what the landlord will deliver. A restaurant going into a former office, for example, raises very different questions than an office replacing an office.
LADBS's bulletin on changing the use of an existing building shows why the paperwork matters: its submittal list includes "Provided copy of 'Certificate of Occupancy' and previous building permits." In our experience, finding the space's permit history early avoids surprises later, especially in older buildings where earlier tenants may have added walls, restrooms or equipment without permits. The landlord's and tenant's work, and the work letter that defines it, are covered in our warm shell vs cold shell guide.
Choose how the project is delivered
In our experience, TI projects are usually delivered one of three ways:
- Design, then bid, then build. An architect completes drawings, contractors bid them and the lowest qualified bid builds. Clear pricing, but the contractor's input comes late.
- Design-build. One team designs and builds. Faster decisions, with the owner relying on that team for both.
- Contractor involved early. The architect designs while a contractor prices and checks constructability along the way. In our experience, this catches long-lead items and budget issues sooner.
The right choice depends on the project's complexity and who is carrying the schedule risk. A simple office refresh with few systems changes can move well with a simple bid; a restaurant, medical office or lab with heavy equipment, ventilation and health or fire reviews usually benefits from having the contractor involved early. In our experience, deciding this before the lease is signed makes the rest of the process smoother.
Walk the space before you design it
In our experience, an existing-conditions walk with the contractor and the designer saves more trouble than any other early step. It answers practical questions: where the electrical panel is and how much capacity it has, whether the HVAC unit serving the suite is sized and working, where plumbing can be tied in, what's above the ceiling and whether earlier tenants left behind walls, wiring or equipment that has to come out. Those answers shape the design, and finding them out after demolition is where budgets and schedules start to slip.
Step 1: Test fit and design
A test fit shows whether the planned layout works in the space. Then the design becomes construction documents. LADBS's submittal requirements for tenant improvements call for "Signature and stamp on all documents by a California licensed architect or engineer" when required and, among its suggested minimum documents, "A complete set of Structural Calculations (for vertical and lateral loads) signed by a licensed engineer or architect in the State of California". In our experience, complete drawings are the single biggest factor in a smooth plan review.
Step 2: The reviews
In the City of Los Angeles, plans for a tenant improvement are typically submitted to the Department of Building and Safety. Depending on the use and scope, other reviews follow. The Los Angeles Fire Department says "Fire Protection Engineers review new construction, change of use, and remodeling projects for buildings and structures containing State Fire Marshal occupancy." Not every tenant space falls into that group, so confirm with your plan reviewer. LAFD adds that "Plans are reviewed for compliance with national, state, and city codes and standards."
Food uses add another agency. LA County Public Health's food facility plan check FAQ says construction, remodeling or tenant improvement work should not begin until plans have been approved by its plan check program and the local building and safety authority, and that remodeled areas or equipment must not be used, stocked with food or used to train employees before receiving field approval. In our experience, restaurant tenants who plan for this review from the first week open far more predictably than those who discover it later.
Step 3: Accessibility and path of travel
In our experience, California's accessibility rules can reach beyond the suite you're altering. The Division of the State Architect's interpretive guide is written for projects under DSA's own jurisdiction, such as public schools, community colleges and state-owned or state-leased essential services buildings, but DSA's guide explains the concept: "Facility alteration projects trigger requirements for accessibility improvements to elements outside the project area of work".
In our experience, a private tenant space in Los Angeles is reviewed by LADBS for accessibility under the California Building Code, and the plan reviewer decides what applies. In our experience, the path of travel, meaning the entrance, the route to the space and the restrooms that serve it, is one of the items most likely to change a TI scope, so it should be looked at during the test fit, not after plan check.
Step 4: Bid package and long-lead items
In our experience, a TI bid package works best when it includes complete drawings, a clear scope split between landlord and tenant, the equipment list and any owner-furnished items. Vague packages produce bids that can't be compared.
Just as important is identifying the items that take longest to get: electrical switchgear or panels, rooftop HVAC units, storefront systems, specialty lighting, kitchen equipment and fire sprinkler or alarm components. In our experience, ordering those as soon as the design allows is often what decides the opening date. Our guide to the tenant improvement electrician covers the electrical scope in detail.
Decisions the tenant should make early
In our experience, the tenant's own decisions are the ones most likely to arrive late. These belong in the design, not in the middle of construction:
- Equipment and its power. Anything with a large electrical, plumbing or ventilation need, from a kitchen line to a server closet.
- Low-voltage systems. Data, phones, security cameras and access control, which need pathways before ceilings close.
- Signage. In our experience, often reviewed separately from the building permit and subject to landlord approval.
- Furniture and fixtures. Layouts that affect outlets, lighting and floor boxes.
- Hours of operation. After-hours HVAC or lighting needs that the building has to support.
Step 5: Construction and inspections
Construction usually follows a familiar order: demolition, framing, rough-in for electrical, plumbing, mechanical and fire protection, inspections of that rough work, insulation and ceilings, finishes and fixtures. In our experience, TI work also depends on coordination with the building: after-hours noise rules, shared utilities, access for deliveries and protection of common areas. A contractor who knows the building manager's rules keeps inspections and deliveries on track.
In our experience, a short weekly meeting with the tenant, the landlord's representative and the contractor prevents most surprises during construction. Open questions get answered, changes get priced and approved before the work, and everyone sees the same schedule.
Step 6: Final sign-off and opening
The job isn't done when the paint dries. In our experience, it's done when final inspections are signed off, any required fire and health approvals are in hand and the landlord accepts the work. If the use changed, the change of use and occupancy paperwork matters too. Our shell and tenant improvement guide covers occupancy for the base building.
For small landlords managing a TI
When the landlord builds the improvements, the same sequence applies, with a different risk. In our experience, the landlord carries the schedule, so a late approval or an unclear tenant request becomes the landlord's delay. Small landlords do best when the tenant's requirements are written down before design starts, the landlord approves changes in writing and the contractor reports progress to both sides. Our shell and tenant improvement guide covers what landlords usually deliver before the tenant's work begins.
Where TI projects lose time
In our experience, days are lost in the same places on project after project:
- Late decisions. Layout changes, finish selections and equipment choices made after the drawings are done.
- Incomplete drawings. Plans that trigger correction after correction in review.
- Surprise reviews. A fire or health review nobody planned for.
- Path of travel. Accessibility work outside the suite discovered at plan check.
- Long-lead items. Equipment ordered after the permit rather than when the design allowed.
- Building constraints. Utility capacity, shared systems or landlord approvals that came late.
- Unanswered questions. Contractor questions that sit without an answer while crews wait.
Some TI projects include bigger building work as well. Our guides to commercial seismic retrofit, ground-up construction and commercial EV charger installation cover those related projects.
The bottom line
Tenant improvement construction runs on decisions and approvals as much as on construction. Confirm the use and the permit history before the lease, choose how the project will be delivered, finish the drawings, plan for every review, order long-lead items early and build with the landlord's rules in mind. Medici Construction Group is one licensed option for tenant improvement construction, holding California A, B and C-10 licenses under CSLB #1114433.
Frequently asked questions
What is tenant improvement construction?
It's the work that turns a leased commercial space into a usable one for a specific tenant: walls, ceilings, lighting, power, plumbing, HVAC changes, finishes and anything the tenant's use requires. In our experience, it runs as a sequence of design, reviews, construction and sign-off rather than a single build.
Who hires the contractor for tenant improvements?
It depends on how the lease sets up the project. Sometimes the landlord builds the improvements, sometimes the tenant hires its own contractor with the landlord's approval, and sometimes it's a mix. Our guide to who handles shell and tenant improvement work covers the split and who pays.
Who reviews the plans for a tenant improvement?
In the City of Los Angeles, in our experience, the Department of Building and Safety reviews the plans, the Fire Department reviews fire and life safety items when the project calls for it, and, for food uses, County Public Health's plan check program is involved.
Does a restaurant tenant improvement need health department approval?
Yes, under LA County Public Health's process. Its food facility plan check FAQ says construction, remodeling or tenant improvement work should not begin until plans are approved by its plan check program and the local building authority, and remodeled areas need field approval before use. In our experience, that review has to be built into the schedule from the start.
What is path of travel in a tenant improvement?
It's the accessible route to and through the altered area, including entrances, restrooms and other elements that serve it. In our experience, alterations can require accessibility improvements outside the area of work, and the plan reviewer decides what applies to your project.
Do I need an architect for a tenant improvement?
Often. LADBS's submittal requirements for tenant improvements call for documents signed and stamped by a California licensed architect or engineer when required. In our experience, simple cosmetic work may need less, but most TI projects with layout, structural, fire or accessibility changes need a design professional.
What slows down a tenant improvement project?
In our experience, late decisions, incomplete drawings, surprise reviews and long-lead equipment cause most delays. The section on where TI projects lose time above covers each one, and most of them can be avoided by deciding early and planning every review from the start.