Look up what a junior ADU costs and the answers barely overlap. Among the three published sources we reviewed, the lowest figure is about $30,000 for a simple interior suite, and the highest is $220,000 for a Los Angeles garage conversion. That's not one market disagreeing with itself. It's three different projects that all carry the same label.
A JADU's price is set mostly by the room you start with and by what the law lets you skip. For utility service and fire and life-safety rules, state law doesn't treat a JADU as a new unit, so it avoids several of the fees and separations that come with one. What's left is mostly the kitchen, the door and, if you add one, the bathroom. This guide shows the published figures, what drives them, and how to read a bid.
Quick answers
- Typical range: about $30,000 to $220,000 across three published sources, depending on the starting room and scope.
- How big: up to 500 square feet, inside the existing home.
- Cheapest path: in our experience, an existing bedroom or suite near a bathroom; a garage costs more because it has to become living space first.
What published JADU cost figures say
These are contractor and designer figures, not market averages, and each assumes a different scope:
| Source and date | Starting room | Figure |
|---|---|---|
| BuildWithAPlan, July 21, 2026 | Interior suite, 300 to 400 sq ft | $30,000 to $50,000 |
| BuildWithAPlan, July 21, 2026 | Attached garage, 400 to 500 sq ft | $45,000 to $80,000 |
| GreatBuildz, updated Sept. 23, 2026 | Garage conversion, Los Angeles | $70,000 to $120,000 |
| Michael Matthews Studio, early 2026 | Bonus room or bedroom, Los Angeles | $80,000 to $150,000 |
| Michael Matthews Studio, early 2026 | 400 sq ft garage, Los Angeles | $120,000 to $220,000 |
GreatBuildz lists what its garage figure includes: "constructing the fourth wall (where the garage door was), installing any interior walls & ceilings, a kitchenette, bathroom, flooring, windows and doors, plumbing, electrical, HVAC, insulation, and connecting to a sewer line." On soft costs, BuildWithAPlan puts permit and plan check fees at $1,000 to $3,500, while Michael Matthews Studio lists LADBS permit fees at $3,000 to $10,000 in Los Angeles. We haven't blended these into an average, because they describe different jobs.
What state law lets a JADU skip
A JADU is cheaper than a new unit partly because, for utilities and fire and life safety, the law doesn't treat it as a new unit. For utilities, Government Code 66338(a) says: "For purposes of providing service for water, sewer, or power, including a connection fee, a junior accessory dwelling unit shall not be considered a separate or new dwelling unit." For fire and life safety, 66337(a) says: "For purposes of any fire or life protection ordinance or regulation, a junior accessory dwelling unit shall not be considered a separate or new dwelling unit."
Both sections still let a local agency apply rules that cover every single-family home the same way, so check with your building department. In unincorporated Los Angeles County, the Public Works JADU requirements list a fire-rated wall as not required and a separate bathroom as not required. A shared bathroom comes with extra conditions under Government Code 66333, covered in our JADU vs ADU guide. Review is also simpler: JADU applications on an existing home are "considered ministerially, without discretionary review or a hearing."
The four choices that set the price
1. The room you start with. A bedroom or suite is already finished living space: insulated, drywalled, wired and heated. A garage usually is not. Converting one means a new wall where the door was, insulation, often a raised or leveled floor, and new windows, which is why the two sources that price both room types put garages higher. Our garage-to-ADU cost guide covers that work in detail.
2. The bathroom. Sharing the main house's bathroom usually avoids the largest single item. Adding one means new fixtures, a drain tied into the building sewer, venting and waterproofing. In our experience, the distance from the new bathroom to the existing drain line matters more than the fixtures you pick.
3. The kitchen. A JADU needs an efficiency kitchen, which under Government Code 66333(f) includes "A cooking facility with appliances" and "A food preparation counter and storage cabinets that are of reasonable size in relation to the size of the junior accessory dwelling unit." Angi's national figures put an added kitchenette at $9,750 to $19,500, with an average of $15,750. That's a national figure for reference, not a Los Angeles quote.
4. The entrance. Under Government Code 66333, a JADU needs its own entrance separate from the main entrance. If the room already has an exterior door, this costs little. If not, a new door means cutting an exterior wall, a header and exterior finish work. Angi's national figures put most exterior door installations at $547 to $2,375, before any wall opening, steps or path.
Garage JADUs: the extra line items
The Los Angeles design studio above breaks a garage JADU into pieces, which shows why garage conversions sit at the top of the range. Its early-2026 figures include interior conversion at $150 to $275 per square foot excluding appliances, garage door replacement at $8,000 to $20,000, utility work at $5,000 to $20,000, and a separate entry path with landscaping at $3,000 to $15,000. Those are one studio's Los Angeles figures, and they assume no major structural work. For the build items themselves, see our guide to junior ADU requirements.
In our experience, the garage door wall is the item that surprises owners most. It isn't just closing an opening: the new wall needs a foundation or curb, framing, insulation, a window, and exterior finish that matches the house. An attached garage is also often a step or two below the house floor, so raising or leveling the floor adds cost before any finish work starts.
Plans, engineering and permits
A JADU still needs drawings. GreatBuildz says "These plans should cost you approximately $4,000-10,000" depending on your needs. BuildWithAPlan lists architectural drawings at a $6,000 flat fee or lower-priced packages. The Los Angeles studio adds structural assessment and engineering at $2,500 to $8,000 where walls or openings change. In our experience, a bedroom JADU with no new openings needs the least engineering, while a garage conversion or a new exterior door in a bearing wall needs the most.
Line items owners miss
In our experience, a few items show up in JADU bids more often than owners expect:
- Electrical capacity. A cooking appliance and a mini-split can push an older panel to its limit; our panel upgrade cost guide covers that cost.
- Sound between rooms. Insulating the shared wall and door is inexpensive during construction and hard to add later.
- Plumbing distance. A kitchenette sink far from existing lines means longer runs and more patching.
- Energy paperwork. In unincorporated LA County, Public Works lists Title 24 energy calculations among the JADU submittals.
Cost per square foot: why a JADU can look expensive
A kitchen and a door tend to cost about the same whether the room is 250 or 500 square feet, so small units carry high per-foot numbers. Some arithmetic on the published figures shows the spread. BuildWithAPlan's interior suite range works out to about $75 to $167 per square foot over its stated 300 to 400 square feet. Michael Matthews Studio's garage range over its stated 400 square feet is about $300 to $550 per square foot. If its interior range applied to a 500-square-foot room, that would be about $160 to $300 per square foot, a little above the studio's own $150 to $275 per-foot conversion figure, which excludes appliances. That's our arithmetic, not a quote. Compare totals, not per-foot figures, when weighing a JADU against a full ADU. A JADU with a high per-foot number can still be the cheaper project overall, because it reuses a foundation, roof, walls and utility service the house already has. The per-foot figure mainly tells you that the fixed items, the kitchen, the door and any bathroom, dominate a small room's budget.
Ways to keep a JADU budget down
In our experience, the biggest savings come from choices made before design, not from cheaper finishes:
- Pick the room with plumbing nearby. A room that backs onto a bathroom or kitchen wall keeps new drain and water runs short.
- Use an existing exterior door. A room that already opens to the outside avoids cutting a new opening.
- Keep the kitchen efficient. The law asks for a cooking facility, a counter and storage, not a full kitchen.
- Decide on the bathroom early. Sharing saves the most, but it brings extra conditions, so settle it before plans are drawn.
When a full ADU makes more sense
In our experience, the math tips toward a full ADU when the space you'd convert is a garage anyway, when you want a private bathroom and a full kitchen, or when you want the unit to stand fully on its own. At that point you're paying for most of an ADU's work while keeping a JADU's size limit. Our ADU construction cost guide covers full ADU pricing, and our JADU vs ADU guide covers the rule differences.
Comparing JADU bids
- Is the bathroom shared or new, and is plumbing priced to the nearest drain?
- What does the efficiency kitchen include, appliance by appliance?
- Is the separate entrance an existing door or a new opening?
- Is an electrical panel upgrade included or excluded?
- Are permits, plans and energy calculations in the price?
The bottom line
A JADU can be the least expensive way to add a unit, but only when the starting room is already living space. Pick the room, decide on the bath, and price the kitchen and door before comparing totals. Medici Construction Group is one licensed option for JADU conversions, holding California A, B and C-10 licenses under CSLB #1114433.
Frequently asked questions
How much does a JADU cost?
Published contractor figures run from about $30,000 for a simple interior suite to $220,000 for a garage conversion in Los Angeles, across the three sources we reviewed. The room you start with, whether you add a bathroom, and how much kitchen you build decide where yours lands.
Is a JADU cheaper than an ADU?
Usually. BuildWithAPlan puts JADU construction costs 60% to 75% below a standalone unit because no new foundation or exterior wall framing is needed, and state law doesn't treat it as a new unit for utility service and connection fees. A JADU in a garage can still cost more than owners expect, since the garage needs walls, insulation and a new wall where the door was.
What type of ADU is the cheapest?
In our experience, a JADU carved out of an existing bedroom or suite with a bathroom nearby is usually the least expensive way to add a unit, because the room is already finished living space. A garage JADU typically costs more, and a new detached ADU typically costs more still.
How big can a JADU be?
Up to 500 square feet. Los Angeles County's planning department describes a JADU as like an ADU but with a maximum size of 500 square feet, built within the main home with its own exterior access. Our JADU vs ADU guide covers the rest of the rules.
How much does it cost to convert a garage into a JADU?
Contractor figures differ widely: one lists $45,000 to $80,000 for an attached garage, another $70,000 to $120,000, and a Los Angeles design studio $120,000 to $220,000 for a 400-square-foot garage. The spread likely reflects differences in scope, location and what each source includes.
Does a JADU pay separate utility connection fees?
Not as a new unit. State law says that for water, sewer or power service, including a connection fee, a JADU isn't considered a separate or new dwelling unit. A local agency can still apply a fee that applies uniformly to all single-family homes.
How much does a JADU kitchen cost?
A JADU needs an efficiency kitchen: a cooking facility with appliances plus a counter and storage cabinets. Angi's national figures put an added kitchenette at $9,750 to $19,500, averaging $15,750. In our experience, plumbing distance and electrical capacity move the price most.