Ask what an ADU costs and you'll get one number. Angi says building one "averages $180,000 but costs range from $40,000 to $360,000." UC Berkeley's Terner Center found that "The median statewide construction cost of an ADU is $150,000, or $250/square foot."

Those describe the build. In Los Angeles, the rest of the bill is design, permits, school fees, utility connections and, for new detached units, solar. Much of it turns on two size lines in state law, 750 and 500 square feet, and on whether you convert space you already have or build new.

Quick answers

  • Typical cost: national guides put most ADUs between about $100,000 and $300,000; the statewide median in the Terner Center survey was $150,000.
  • Cheapest type: converting a garage or other existing space. New detached construction costs the most.
  • The 750 sq ft line: state law bars impact fees on an ADU with 750 square feet of interior livable space or less.
  • The 500 sq ft line: since January 2026, ADUs under 500 square feet of interior livable space are treated as not triggering school fees.
  • Solar: a newly built detached ADU generally needs its own solar PV system under the 2025 Energy Code, with exceptions for very small systems.

What an ADU costs to build

The national cost guides agree on the shape of the numbers, if not the exact figures. Angi says an ADU "costs about $150 to $300 per square foot on average, but some ADUs cost over $600 per square foot." HomeGuide puts the range at "$100 to $300 per square foot for an attached, detached, or converted secondary living space."

The Terner Center's statewide survey shows what owners actually paid: "37 percent" cost less than $100,000 to build, and "71 percent of ADUs cost less than $200,000." An older Terner Center report put a Los Angeles figure on it: "In Los Angeles, the average cost estimate is $148,000." That report is from 2020, so treat it as dated.

In our experience, LA projects land higher than a national average because of labor costs, hillside and tight-access lots, and the fees covered below.

Cost by ADU type

Type matters more than finishes. Here is how the two national guides break it down:

ADU typeAngi (total)HomeGuide
Garage conversion$60,000 to $150,000$50 to $200 per sq ft
Attached new construction$100,000 to $216,000$125 to $225 per sq ft
Above-garage construction$128,000 to $225,000Not listed separately
Detached new construction$110,000 to $285,000$150 to $250 per sq ft
Prefab or modularNot listed separately$80 to $160 per sq ft (unit)

A conversion is cheaper because the foundation, walls and roof already exist; see our garage-to-ADU cost guide. A detached unit needs all of them, plus its own utility runs across the yard. In our experience, the prefab figure covers the unit only; foundation, trenching, crane, permits and site work are extra, and in LA they can close much of the gap with site-built. See our prefab ADU cost guide.

Cost by size: 400 to 1,000 square feet

To turn per-square-foot figures into a budget, multiply. Here is Angi's typical $150 to $300 per square foot applied to common sizes. These are build costs only, before soft costs and fees. See also our 1,000 sq ft ADU cost guide.

ADU sizeBuild cost at $150/sq ftBuild cost at $300/sq ft
400 sq ft$60,000$120,000
500 sq ft$75,000$150,000
600 sq ft$90,000$180,000
750 sq ft$112,500$225,000
800 sq ft$120,000$240,000
1,000 sq ft$150,000$300,000

How much does a 500 sq ft ADU cost? At those rates, roughly $75,000 to $150,000 to build. HomeGuide's detached range works out to "$90,000 to $150,000" for 600 square feet. In our experience, small units cost more per square foot, because the kitchen, bathroom, panel and utility connections cost about the same at 400 or 900 square feet.

The two size lines in state law

California sets two thresholds that change what you owe the government, not the builder.

750 square feet: impact fees

State law says a local agency "shall not impose any impact fee upon the development of an accessory dwelling unit that has 750 square feet of interior livable space or less." Above that, fees "shall be charged proportionately in relation to the square footage of the primary dwelling unit." SB 543 moved this rule from section 66324 to 66311.5 in 2026.

In our experience, impact fee amounts depend on the agency and project. The point is the line: a design with 740 square feet pays none, while one with 800 can be charged a share. Separately, the City of Los Angeles says its Affordable Housing Linkage Fee does not apply to "second dwelling units (accessory dwelling units)."

500 square feet: school fees

School districts charge developer fees on new residential space. California's Education Code lets them charge on added space only when the new space adds more than 500 square feet of assessable area. SB 543 made that explicit for ADUs: starting in 2026, an ADU that "contains less than 500 square feet of interior livable space" is treated as construction that does not add 500 square feet.

The State Allocation Board raised the maximum Level 1 residential rate from $5.17 to $5.38 per square foot in January 2026. In practice, a 480-square-foot ADU owes no school fee, while a 520-square-foot ADU charged on its full footage would owe about $2,800 at $5.38. In our experience, LAUSD collects it for most City of LA lots, so confirm the rate with the district before finalizing size. For the smaller JADU category, see our JADU vs ADU guide. What a JADU costs is covered in our JADU cost guide.

The rest of the bill: soft costs, permits, utilities and solar

Design and engineering

Angi says "Simply designing your ADU will cost 10% to 15% of the total cost of your project," with "Architect fees: $125–$250 per hour" and structural engineers at $70 to $250 per hour. In our experience, a detached ADU also needs a Title 24 energy report, and hillside or poor soil adds a soils report. Our LADBS permit fee calculator guide explains what the city's estimate covers.

Permits and plan check

Angi puts "the average cost of a building permit for ADUs in California" at $10 to $12 per square foot (about $5,000 to $6,000 at 500 square feet). For a City of LA number, LADBS points applicants to its Permit Fee Calculator, which it describes as "an online service that can assist in permit fee calculations." LA's ADU rules live in LAMC Section 12.22.A.33; our ADU permit guide covers the review steps.

Garage in Los Angeles being converted into an ADU with new framing and a window where the door was

Utility connections and service upgrades

Conversion and new construction split again. For an ADU within the existing or proposed space of a single-family home, or within an existing accessory structure, state law says the agency or utility "shall not require the applicant to install a new or separate utility connection directly between the unit and the utility or impose a related connection fee" or capacity charge. The exception is a unit built together with a new single-family home. For other ADUs, a separate connection can be required, but the fee "shall be proportionate to the burden of the proposed accessory dwelling unit" and "shall not exceed the reasonable cost of providing this service."

In our experience, the bigger surprises are on your side of the meter. An older house often lacks the capacity for a second kitchen, heat pump and water heater, so a panel upgrade gets added; see our electrical panel upgrade cost guide. A detached unit also needs a sewer line to the main lateral, and a cracked old clay lateral is better found before the new line ties in; see our sewer line replacement cost guide. Long trenches across a yard add up quickly.

Solar for new detached ADUs

California's Energy Commission says that under the 2025 Energy Code, "PV requirements apply to all newly built single-family dwellings," which includes a newly built detached ADU. The same guidance says the rule "Does not apply to additions or alterations," so conversions and attached additions generally skip it.

Two exceptions help small units: no system is needed "when required PV size is less than 1.8 kWdc," and the required size "can be reduced by 25% if a battery energy storage system (BESS) is installed."

Small detached ADU in a Los Angeles backyard with solar panels on the roof

Parking you usually don't have to replace

When a garage or parking space is converted or torn down for an ADU, "the local agency shall not require that those offstreet parking spaces be replaced."

How LA homeowners keep the number down

Use what's already built. A garage or accessory structure brings a foundation and roof, and state law says "No setback shall be required for an existing living area or accessory structure." New units that aren't conversions need "a setback of no more than four feet from the side and rear lot lines." In our experience, an old garage still needs a structural check, since a cracked slab can erase part of the savings.

Design to the lines. Keeping interior livable space at or under 750 square feet avoids impact fees, and under 500 avoids school fees.

Look at LA's standard plans. LADBS runs a Standard Plan Program of ADU designs "reviewed and pre-approved by LADBS for compliance with the Building, Residential, and Green Codes." LADBS says "Using standard plans shortens the time needed to review the plans through plan check, and corresponding permits are issued more quickly." See our guide to ADU plans in Los Angeles compares standard, County, stock and custom plans.

Know the review clock. A permitting agency must approve or deny a complete ADU application "within 60 days from the date the permitting agency receives a completed application." In our experience, the clock starts only when the application is complete, so thorough drawings save the most time.

Don't build the budget on a grant. CalHFA's ADU program offered "grants up to $40,000 to reimburse pre-development and non-recurring closing costs," but its page says "The latest round of ADU funding has been fully allocated." See our guide to financing an ADU for loan options.

After it's built: property tax

An ADU adds to your property tax, but only for the new part. The Board of Equalization says "The new base year value of the new construction is the increment of market value, if any, that the assessor estimates has been added to the overall property. The value of the existing property is not affected." In our experience, the assessor's number is usually close to the construction cost, so budget for property tax on roughly what you spent.

For more room for your own household instead, see our home addition cost guide.

Getting ADU bids you can compare

In our experience, ADU bids are hard to compare because each draws the line differently; our guide to choosing an ADU builder covers how to judge the builders behind them. Make sure every bid says:

  • Whether design, engineering, the Title 24 report and a soils report are included, or are yours to buy.
  • Whether permit, plan check, school and utility fees are in the price or allowances.
  • What happens at the utilities: trench length, new sewer line, electrical panel or service upgrade, and water line.
  • Whether solar is included for a detached unit, and at what size.
  • Site work: demolition, grading, access, and hauling.
  • Exact interior livable square footage, since it drives the 750 and 500 sq ft lines.

A low bid that leaves out utilities and fees is not a low bid. Check any contractor's license first; see how to check a California contractor's license walks through it. Medici Construction Group is one licensed option for ADU construction, holding California A, B and C-10 licenses under CSLB #1114433.

Frequently asked questions

How much does it cost to build an ADU in Los Angeles?

Most ADUs fall between about $100,000 and $300,000 in national guides, and the Terner Center's statewide median was $150,000. In our experience, LA projects run toward the higher end once design, fees, utilities and solar are added to the build price.

How much does a 500 sq ft ADU cost?

At $150 to $300 per square foot, roughly $75,000 to $150,000 to build, before soft costs and fees. Keeping the unit under 500 square feet of interior livable space also avoids school fees under the 2026 rules, which can make the smaller size worth choosing.

What is the cheapest type of ADU to build?

A conversion of existing space, usually a garage, because the foundation, walls and roof already exist. Angi puts garage conversions at $60,000 to $150,000, compared with $110,000 to $285,000 for detached new construction. Prefab pricing usually covers the unit only.

Do ADUs pay impact fees in California?

Not if the ADU has 750 square feet of interior livable space or less. Larger ADUs can be charged impact fees in proportion to the size of the main house, under Government Code section 66311.5. Design close to 750 square feet deserves a careful measurement.

Does a detached ADU need solar panels in California?

Generally yes, if it is newly built. The 2025 Energy Code treats it as a new single-family dwelling, though no system is required if the calculated size is under 1.8 kWdc, and a battery can reduce the required size by 25%. Conversions and additions generally skip it.

Does building an ADU raise property taxes?

Yes, but only on the value the ADU adds. The Board of Equalization says the existing property's value is not affected. In our experience, the assessor's number is usually close to the construction cost, so budget for property tax on roughly what you spent.

Is the CalHFA ADU grant still available?

Not right now. CalHFA's page says the latest round of ADU funding has been fully allocated, after offering grants up to $40,000 for pre-development and closing costs. Check calhfa.ca.gov for any new round before you plan around it, and budget without it.

Is building an ADU worth the cost?

It depends on your rent or family-housing plans and your lot. Compare the full cost, including fees, utilities and the added property tax, against the rent or use you expect. Our guide on how much value an ADU adds covers what appraisal data shows.